Aquatic Complex: Construction Photos

Aquatics Construction Image Update Loading image. Please wait
Week one of construction. The light posts have been taken down.
forward arrow
back arrow
Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction Aquatic Complex Construction
10/6/09: Week one of construction. The light posts have been taken down.
10/6/09: Week one, not much happening yet.
10/13/09: Week two, all plants have been removed as well as the parking surface. The site is being prepared for the new aquatic addition.
10/13/09: Week two, big piles of dirt have been brought in to solidify the ground.
10/20/09: Week three, the site work continues. A large pump has been buried to remove ground water from the site.
10/20/09: Week three, more site work.
10/27/09: Week four, lots of digging. A few forms have been dug getting ready for concrete.
10/27/09: Week four, large footings for the mechanical areas have been poured. We are moving right along.
11/3/09: Week five, footings have been poured along the west side of the new facility.
11/3/09: Week five, the large footing for the mechanical area has been poured. Framework for the walls to the mechanical areas are going up.
11/10/09: Week six.
11/10/09: Week six.
11/17/09: Week seven, workers are preparing to remove the brick from the South wall of the facility.
11/17/09: Week seven, brick removal begins.
11/19/09: Week seven, a view of the construction from the Norco Building. All bricks have been removed.